Rentricity Projects
Site Assessment
Click on Specs for details
Featured Projects

Water Treatment Plan, Keene, NH
Flow: 700-1200 gpm
Presure: ~75 PSI
kW: 62
Intertie: Net-Metered
Raw Water
Startup: 2012
Multi-Turbine/Net Zero Energy

Flow Control Vault, Halifax, Nova Scotia
Flow: 2.4 MGD Pressure: ~40 PSI
kW: 32
Intertie: Tariff
NSF 61/372: Yes
Start-up: 2014
Features: Vertical Turbine

Pump Station, Westmoreland, PA
Flow: 2.4 MGD
Pressure: 60 Feet
kW: 30
Intertie: Behind Meter
Raw Water
Start-up: 2010
Mandated Release

Above Ground Regulator Station, Anchorage, AK
Flow: 4-5 MGD
Presure: ~35 PSI
kW: 45
Intertie: Net-Metered
WQA Cert: NSF 61/372
Startup: 2021
Main Distribution System

Water Treatment Plant, Manitou Springs, CO
Flow: 500-1400 gpm
Pressure: 150-250 PSI
kW: 75
Intertie: Net-Metered
Raw Water
Start-up: 2022
Features: Ultra High Pressure

Irrigation System, RIchmond, UT
Flow: 2-12 MGD
Pressure: 175-250 Feet
kW: 360
Intertie: Net-Metered
Raw Water
Start-up: 2016
8,000 Acre Multi-Site/3 Turbines